Lake Champlain Bridge Replacement

  • Client:
    Flatiron Construction Corp
  • Completion Date:
    September 2011
  • Collaborators:
    Erdman Anthony
    HNTB
  • Project Type:
    Marine Infrastructure
  • Service Categories:
    Marine Engineering
  • Challenge:
    Two-barge transport of 402-foot bridge span.

A VITAL LINK.

After an inspection revealed significant deterioration of the 80-year-old support piers, the New York State Department of Transportation suddenly closed the old Lake Champlain Bridge. The bridge connected Crown Point, NY to Chimney Point, VT, and its closure had a huge impact on the local community, separating residents from important services and forcing thousands to add 85 miles to their daily commute. A replacement was needed fast.

As part of their expedited construction strategy, the project team decided to fabricate the center bridge archway span off site while the bridge approach spans were being built in situ. The center span was then to be floated in and lifted into place. Flatiron contracted Glosten to provide engineering to support the archway span’s loading and transport to the bridge site and to provide onsite construction support.

JDS_2147

RECONNECTING A COMMUNITY.

Two barges, one supporting each end of the span, were needed for transport. The barges had to support the 1,118-ton weight of the bridge, and the two-tug transit, which included some maneuvering from the fabrication site, had to be carefully synchronized so as to not impart bending and compression stresses that would damage the span.

Glosten engineers inspected the structure and analyzed the stability of both barges to ensure they could safely support and transport the bridge span. They then designed the seafastenings that secured the span to the barges and developed the tow plan for the transport operation. They also devised a way of determining the barges’ relative positions while underway and were on site to monitor the span’s loading during transport to be sure its bending and compression limits were not exceeded. After a four-hour transit, the span arrived safely at the bridge site and was raised into position that same day. The new bridge was opened on November 7, 2011, just over two years after the old bridge was closed.